AIRFIELD CONSTRUCTION USING RTX-300
KAMBAUK (MYANMAR) SITE
   
 
AIRFIELD DETAILS
Overall Length :
Runway Length :
Runway Width :
Treated Depth ( RTX-300 ) :
Sealed With :

880 Meters
800 Meters ( between turnaround areas )
20 Meters ( + 2 meter RTX-88 clear-sealed shoulder )
30 + centimeters
RT3-55 & sand ( two layers )

 
MINE HAUL ROADS CONSTRUCTED WITH RTX-300
BATU HIJAU (INDONESIA)
   
 
RESORT ROADS USING RTX-300
PHU YEN PROVINCE (VIETNAM)
     
 
PLANTATION ROADS USING RTX-300 & T3-55
RIAU PROVINCE (SUMATRA)
     
Palm Oil Plantation road construction in Sumatra - May 2004


Applying RT3-200 Emulsion treatment
Sumatra May 2004
T3-200 Emulsion treated road after 6 + Months
Sumatra Dec. 2004
 
OFFSHORE PLATFORM FABRICATION PLANT
BATAM, INDONESIA
   
 
REFERENCE LETTER McDERMOTT BATAM, INDONESIA

" The access road and entrance at the heavy rolling mill is still as solid as the day you put it in…frankly I was skeptical of the claims you made for the product. I figured that, in time, owing to the heavy rainfall here, it would be washed away.
"


Jim Drane
Gen. Superintendent,
McDermott International
Batam, Indonesia
 